Hestia Housing Association
Value:
£100k
Project:
To carry out the fit out of the 3rd floor of Sovereign Court.
Background:
Orion Group were employed by Hestia Housing Association to help them relocate from their old building in Ealing to new modern premises.
Scope of Works:
This consisted of:-
- Detailed designs
- Specifications
- Detailed cost plan
- Programme of works
- Health & Safety Plan
Project Work Included:
- Replacement Ceilings
- Mechanical Services
- Electrical Services
- Data cabling
- Fit out of Ground & First Floors
- Partitioning & Doors, including specialist glazed elements
- Beverage preparation areas
- Furniture installation
Summary:
“Delivered on time and to agreed costs, despite multiple changes to the original specification. Thank you for all your hard work on this fit-out – the result is great and I’ve had very positive feedback from all my colleagues and our CEO, who were suitably impressed. I know there were many people involved at Orion in this project, but my special thanks to you as the person we constantly hounded – it was a real pleasure working with you.”
Vanessa Coutinho, Facilities Manager