Tandberg
Value:
£1.4m Design and fit out
Project:
Design and fitting out of Tandberg's new EMEA Headquarters in Staines
Background:
Orion Group were employed as Consultants to prepare detailed designs and cost plans.
Tandberg then decided to continue working with Orion Group and the works commenced on a fast track contract.
Scope of Works
This consisted of:
- Detailed designs
- Specifications
- Detailed cost plan
- Programme of works
- Health & Safety Plan.
Project Work Included:
- Replacement ceiling
- Mechanical Services
- Electrical Services
- Data cabling
- Fit out of the Ground and First Floors
- Partitioning & doors, including specialist glazed elements
- Beverage preparation areas
- Specialist furniture, designed and manufactured to meet specific requirements
- Furniture installation